MEASURED
MILE
ANALYSIS OF
PRODUCTIVITY
LOSS
AN ‘ARTIFICIAL’
OPINION
David Brown
Diales Quantum Expert
The measured mile analysis is a technique used to identify
and quantify productivity loss on construction projects. It
involves measuring the productivity of a particular task or
activity over a set distance, referred to as the "measured
mile." This technique allows construction professionals
to identify factors that are causing productivity loss and
implement strategies to improve efficiency.
One of the key benefits of the measured mile analysis is that
it provides a clear and objective way to assess productivity. By
measuring the same task or activity over a set distance, it is
possible to eliminate variables that could affect the results.
This allows construction professionals to focus on specific
factors that are impacting productivity, such as equipment
malfunctions, delays due to weather, or inefficient work
processes.
To conduct a measured mile analysis, construction
professionals typically select a task or activity that is
representative of the work being performed on the project.
This could be something as simple as excavating a certain
amount of soil or installing a specific type of piping. The task
is then performed over a set distance, with the productivity
being measured at various points along the way.
16
Once the data has been collected, it is analyzed to identify
areas where productivity is lagging. This may involve looking
at factors such as the amount of time spent on the task, the
amount of material used, or the number of workers involved.
By identifying the root cause of the productivity loss,
construction professionals can implement strategies to
improve efficiency.
There are a number of strategies that can be used to improve
productivity on construction projects, including investing in
new or more efficient equipment, improving work processes,
and providing additional training to workers. By using the
measured mile analysis, construction professionals can
identify specific areas where these strategies are needed and
implement them in a targeted and effective manner.
Overall, the measured mile analysis is an effective tool for
identifying and addressing productivity loss on construction
projects. By providing a clear and objective way to assess
productivity, it allows construction professionals to identify
the root causes of inefficiency and implement strategies to
improve efficiency and reduce costs.